Install Formbo's two-layer roofing-felt package
A guided checklist for Formbo's calculated roofing package, with MIDA YEP2200 underlay and MIDA SELF KSK self-adhesive top layer, for gable and pent roofs.
Four quick facts about the package
Two named layers
MIDA YEP2200 is the underlay. MIDA SELF KSK is the self-adhesive top layer installed above it.
Calculated for the building
Quantities in LOG-ROOFING-PACKAGE are calculated from the roof of your configured building.
Finishes for both roof types
The guide shows separate finishing sections for gable and pent roofs. Follow the one that matches your building.
Tongue-and-groove timber deck
This guide is for Formbo's planed tongue-and-groove pine roof boards, nominally 22 × 95 mm.
Show the guide contents
Before you begin
Plan all work at height from ground level before installation begins.
Plan the work at height
Plan access, fall protection, material handling and rescue before anyone goes onto the roof.
Check first
- Decide how materials will be raised without anyone carrying rolls up a ladder.
- Review the work sequence and decide who will stop the work if conditions change.
Ready for the next step when
Access, protection, material handling and the rescue plan are ready and understood by everyone on site.
Weather, fall risk and structural uncertainty are stop conditions, not problems to solve while on the roof.
Package and tools
Lay out the roofing components and prepare the tools at ground level before you begin.
Check that everything is present
Match the delivery to the order and gather the tools before any material is taken onto the roof.
Check first
- Lay out the components somewhere dry at ground level and check them against the order and product labels.
- Set aside damaged or unrecognised items. If any items are missing, damaged or unrecognised, contact Formbo before continuing.
Ready for the next step when
Every package component is present, undamaged and matches the order. The tools are gathered and ready.
Roof boards and cutting
Inspect the roof boards before they are covered and prepare the cutting work at ground level.
Inspect the roof boards
Examine the entire tongue-and-groove deck before any part is concealed.
Check first
- Check that the surface is clean, dry and free from sharp objects.
- Look for damage, movement, proud fixings and local unevenness.
- Stop and have the deck assessed by a competent person if the structure or load-bearing capacity is uncertain.
Ready for the next step when
The complete deck is documented and approved, with no moisture, damage, movement, sharp objects or unresolved changes in level.
Measure and cut at ground level
Make a cutting list from the approved package drawing and distinguish the narrow starter strip from the full-width underlay sheets.
Check first
- Measure the roof slope and compare it with the drawing's joint positions and folds.
- Mark the narrow starter strip and each full-width underlay sheet for its position without damaging the surface.
- Support the starter strip and full-width sheets while cutting, then keep them separate and protected until installation.
Ready for the next step when
The starter strip and first full-width underlay sheet are identified, correctly oriented and checked against the drawing without guessing any installation dimensions.
Build the eaves and protected edges
Bond the starter strip, nail the eaves flashing and screw the triangular battens into the roof boards before laying the full underlay.
Bond the starter strip and nail the eaves flashing
A narrow strip of MIDA YEP2200 is bonded directly to the roof boards before the eaves flashing is placed over it and nailed in position.
Check first
- Dry-position a narrow strip of MIDA YEP2200 directly on the roof boards along the eaves.
- Apply roofing mastic as shown in the detail and bond the strip without creases.
- Dry-position the eaves flashing over the bonded strip and check its direction, corners and joints.
- Nail the flashing using the fixing arrangement and sequence shown in the detail.
Ready for the next step when
The starter strip lies smoothly against the roof boards and the eaves flashing lies straight, flat and continuous above it.
Screw the triangular battens to the roof boards
Install the triangular battens directly into the roof boards before laying the full underlay.
Check first
- Dry-position the triangular battens and check their positions, junctions and corners against the drawing.
- Screw the triangular battens directly into the roof boards using the fixing arrangement shown in the detail.
- Check that every batten is secure and that no fixing stands proud.
Ready for the next step when
The triangular battens are secure directly in the roof boards and ready to be covered by the underlay.
Install MIDA YEP2200 as the underlay
MIDA YEP2200 forms layer 1. It must not be left as the sole finished roof layer.
Align the first full underlay sheet
Lay the full underlay sheet over the prepared eaves and bring it up and over the triangular battens as shown in the detail.
Check first
- Dry-position a full sheet of MIDA YEP2200 over the prepared eaves detail and check its line from both roof edges.
- Bring the underlay up and over the triangular battens as shown in the detail and smooth the material without stretching it.
- Fix only within the zones and with the fixings stated in the approved instructions.
Ready for the next step when
The full underlay sheet lies straight, flat and undamaged over the eaves and up and over the triangular battens.
Continue the underlay across the roof
Position each new sheet to the approved water-shedding sequence and inspect every junction before it is covered.
Check first
- Dry-position the next sheet and inspect the full lap area.
- Clean and dry every surface that will meet.
- Close the joint and complete fixing or sealing exactly as instructed.
Ready for the next step when
Every lap and end joint is complete, clean, closed and recorded before the next sheet covers the area.
Approve the complete underlay
Make this a clear hold point before MIDA SELF KSK is taken onto the roof.
Check first
- Trace every joint and edge, including areas that will be hard to see later.
- Check that the surface lies flat, with no holes, creases or open junctions.
- Photograph the complete layer and every end joint before starting layer 2.
Ready for the next step when
Layer 1 is complete, flat, documented and approved against the package drawing's hold points.
Install MIDA SELF KSK as the top layer
Layer 2 is self-adhesive. Remove the release film and press the surface only when the sheet is correctly positioned and the underlay meets the approved surface requirements.
Align the first top-layer sheet
Check the complete position before exposing the adhesive surface.
Check first
- Dry-position the sheet with the release film intact and check it against both edges.
- Remove the release film in controlled stages without contaminating the adhesive.
- Press the specified area evenly with the correct tool and inspect it at once.
Ready for the next step when
The first top-layer sheet is straight and flat, with a clean, evenly pressed bond and no trapped creases.
Complete the top-layer sheets and joints
Before removing the release film, check how every new top-layer joint relates to the layer 1 joints.
Check first
- Dry-position the next sheet and compare the joints in both layers with the drawing.
- Clean the surfaces, expose the release film in stages and make the joint in the stated sequence.
- Press the whole joint area and inspect the edge, end joint and connections before continuing.
Ready for the next step when
Layer 2 lies flat, every joint is closed, and all joint offsets and seals have been recorded.
Choose the finish for your roof type
Complete only the branch that matches the building: the ridge for a gable roof or the high edge for a pent roof.
- Gable roof
Complete the gable-roof ridge
Coordinate both roof slopes so the ridge forms one continuous detail.
Check first
- Dry-position the material from both roof slopes across the ridge area.
- Form the folds, any additional strip, mastic and fixings in the order shown on the drawing.
- Inspect the full ridge from both sides before completing the edge flashings.
Ready for the next step when
The ridge is continuous, closed and recorded along the full length of the gable roof.
- Pent roof
Complete the high edge of the pent roof
Verify the pitch before closing the high edge. Roofs below 5° remain blocked until the 3° build-up has signed technical approval.
Check first
- Stop if the roof pitch is below 5° and there is no project-specific signed approval.
- Dry-position the membrane and edge components without exposing adhesive surfaces.
- Build and inspect the high edge in the sequence shown on the drawing.
Ready for the next step when
The pitch is approved and the high edge is continuous, closed and documented.
Inspect and record the finished roof
Finish only after every roof slope, edge and relevant roof-type branch has been checked from a protected working position.
Install the final flashings and inspect the roof
Close corners and edge flashings to the drawing, then inspect the complete system from the eaves to the ridge or high edge.
Check first
- Install the final flashings in the stated sequence and inspect every corner.
- Trace all joints, edges and water-shedding routes, and remove loose material.
- Photograph the roof and retain product names, article numbers, batch details, the drawing and the instructions used.
- Plan future checks to the approved product and maintenance information, and after severe weather or visible damage.
Ready for the next step when
There are no open joints, damaged areas, loose parts or obstructed water-shedding routes, and the whole installation has been recorded.